FlagstoneDue-diligence report
Feasibility Study · NI 43-101

Schaft Creek Project

Copper Fox Metals Inc.
Location
Northwestern British Columbia, Canada (Cassiar/Liard Mining Division, ~61 km south of Telegraph Creek)
Effective date
January 23, 2013
Prepared by
Tetra Tech (Document No. 1053440200-REP-R0003-03.1); QPs include Hassan Ghaffari, P.Eng., Jianhui (John) Huang, Ph.D., P.Eng., Daniel Friedman, P.Eng., Robert Sinclair Morrison, Ph.D., P.Geo. and others; supporting consultants Moose Mountain Technical Services, McElhanney, Knight Piésold
Source
NI 43-101 technical report (filed PDF)
❝What this is. A technical report runs hundreds of pages to justify a few headline numbers. Flagstone read the whole thing and checked whether the testwork and data behind those numbers actually hold them up. Below: the five independent verdicts, the facts as reported, and every issue we found - explained in plain terms.
— Project at a glance

Facts reported from the document — not graded. Flagstone's verdicts follow below.

Ownership & deposit
Owner
Copper Fox Metals Inc.
Deposit type
porphyry copper (Cu-Mo-Au-Ag)
Location
Northwestern British Columbia, Canada (Cassiar/Liard Mining Division, ~61 km south of Telegraph Creek)
Resource & reserve
Cut-off
Reserve: $6.60/t NSR cut-off; resource domain grade shells at 0.25% CuEq; historic 2011 resource at 0.12% CuEq; current resource reporting cut-off not in extracted text
Economics
IRR
10.13
Payback
6.48
Price deck
copper US$3.25/lb, gold US$1,445/oz, silver US$27.74/oz, molybdenum US$14.64/lb, exchange rate Cdn$1.00:US$0.97
— Dimensions at a glance
Environmental, permitting & social licencePartially supported↓Metallurgy & recoverySoundly supported↓QA/QC & data verificationSoundly supported↓Economics & costsSoundly supported↓Resource & reserveSoundly supported↓

Each dimension is graded independently on this report's own study stage - not combined into one score.

Metallurgy

This section is Soundly supported.

In plain termsThe science behind the numbers is solid for this stage - a couple of gaps are what keep it from the top mark.
StronglySoundlyPartiallyThinly
5 views
Soundly supported
Is the testwork thorough enough for this stage?

Judged against the Part 3 FS column: bench flotation (expected) - present across six programs; variability composites 'many, spanning grade and spatial variability' (required) - 34 individual variability samples plus multiple zone and mine-schedule composites covering Liard, Paramount and West Breccia and head grades from 0.15 to 1.17% Cu; locked-cycle testing (required) - ~30 LCTs including duplicates at three grind sizes; mineralogy→recovery linkage (required) - modal mineralogy, liberation estimates tied to a stated 50-55% copper-sulphide liberation threshold justifying the 150 µm primary grind, gold deportment by ADIS, and bulk-concentrate liberation supporting the Cu-Mo separation design; deposit-specific flowsheet (required) - SABC/bulk float/regrind/three-stage cleaning/Cu-Mo separation with ferric chloride moly leach, supported by multi-sample comminution and SABC simulation at the selected 130,000 t/d rate. Pilot-scale work (2007 and 2008 campaigns) is present and at FS is only expected where warranted, so it is treated as supporting rather than required. Cu-Mo separation was tested by five locked-cycle tests, so the FS-stage expectation for separation testwork is met. What holds this at B rather than strongly supported is the metallurgical framework: the recovery model carried into the block model (Table 13.35) is a set of head-grade-only logarithmic equations applied uniformly to the whole deposit, with no domain-specific relationships despite the report's own statements that variability-sample performance showed 'a very poor correlation' traceable to 'significant differences in mineralogy between the samples', and that PRA and G&T results for the Paramount and West Breccia zones 'were conversely different... The reasons for the difference in the metallurgical performance are not clear.' The QP recommends further testwork on those zones. Recovery at head grades outside the tested range is 'assumed based on the test results and experience'. At FS stage an undomained, head-grade-only model with acknowledged unexplained scatter is a real weakness and pulls the letter down from the A the breadth of testwork would otherwise support.

QA/QC

This section is Soundly supported.

In plain termsThe assay data is well-controlled for this stage, with a few disclosure gaps off the top mark.
StronglySoundlyPartiallyThinly
4 views
Soundly supported
Was the control program designed to accepted standards and actually run?

Clears every check. Worth a look: the CRM suite doesn't fully span the grade range, the blank program is lightly described, primary-lab accreditation/independence is stated but not fully evidenced.

Economics

This section is Soundly supported.

In plain termsA solid economic disclosure for this stage, with a few disclosure gaps off the top mark.
StronglySoundlyPartiallyThinly
4 views
Soundly supported
Are the capex/opex numbers as precise as the stage claims?

Clears every check. Worth a look: sustaining and closure capital are folded in but not broken out.

Environmental

This section is Partially supported.

In plain termsThe permitting and social groundwork is laid out, but the environmental work isn't carried to this stage's bar.
StronglySoundlyPartiallyThinly
4 views
Partially supported
Can it get permitted and built?

No single finding here is disqualifying, but the disclosure gaps stack up past the bar for a feasibility study - together they hold this to Partially. The gaps: the permit timeline is optimistic but not implausible for the jurisdiction, the EIS/baseline work is still maturing for the stage, Indigenous engagement is described as consultation rather than documented consent and the community/social-impact assessment is lightly detailed.

Resource

This section is Soundly supported.

In plain termsA sound resource for this stage - the estimate and classification hold up, with a few disclosure gaps off the top mark.
StronglySoundlyPartiallyThinly
4 views
Soundly supported
Is the estimate built and classified defensibly?

Clears every check. Worth a look: the estimation method is disclosed but its fit to the grade distribution isn't fully justified, estimate validation is disclosed in outline (visual / global; local swath not shown), the QA/QC behind the input assays is Soundly-supported - carried in from the §11–12 assessment.

How Flagstone grades. Each dimension is scored on two things - is the work thorough enough for the project’s stage, and can you trust the numbers as reported? The weaker of the two sets that dimension’s verdict. Dimensions are graded independently on the report’s own stage and never combined into one score. Key figures are measured against similar-stage projects.
Flagstone assesses the defensibility of a report’s technical disclosure. It is a screening tool - not technical, investment, or qualified-person advice.